The 14-mile, tolled expressway will be built in three phases, running from SR 417 near Boggy Creek Road in Orange County to Nova Road in Osceola County. SR 534 will feature two lanes in each direction and seven interchanges.
Building Sr 534
Once the project is complete, SR 534 will include seven new interchanges, more than 30 new mainline bridges and a modern and progressive design that includes roundabouts, to keep traffic moving with fewer conflict points.
Connectivity and aesthetics will also be enhanced with the addition of pedestrian-friendly shared use paths and sidewalks along local roads and treatments such as planter walls and native landscaping along the expressway.
SR 534 will be designed and constructed in phases and segments – Phases 1, 2 and 3. Each phase will be divided into segments. Below is a description of each phase and the status of design and construction:
Phase 1 – SR 417 to Narcoossee Road
Status: Design
Click on the map icon for more details on this phase of the project.
• Distance: 0.6 miles
• Design Start: May 2023
• Anticipated Design Completion: Spring 2026
• Anticipated Construction Start: Spring 2027
• Distance: 2.8 miles
• Design Start: February 2025
• Anticipated Design Completion: Winter 2027
• Anticipated Construction Start: Spring 2028
• Distance: 2.4 miles
• Design Start: May 2023
• Anticipated Design Completion: Winter 2026
• Anticipated Construction Start: Summer 2027
• Distance: 1.4 miles
• Design Start: June 2023
• Anticipated Design Completion: Summer 2025
• Anticipated Construction Start: Winter 2027
• Distance: 1.9 miles
• Design Start: January 2023
• Anticipated Design Completion: Winter 2026
• Anticipated Construction Start: Spring 2027
Phase 2 – East of Narcoossee Road to Cyrils Drive
Status: Design
Click on the map icon for more details on this phase of the project.
Phase 3 – Cyrils Drive to Nova Road
Status: Planned
The design of this phase could begin as early as 2026.
• Distance: 1.9 miles
• Design Start: Spring 2026
• Anticipated Design Completion: Winter 2028
• Anticipated Construction Start: Summer 2029
• Distance: 1.9 miles
• Design Start: Summer 2026
• Anticipated Design Completion: Spring 2028
• Anticipated Construction Start: Fall 2029
• Distance: 1.8 miles
• Design Start: Fall 2026
• Anticipated Design Completion: Summer 2028
• Anticipated Construction Start: Winter 2030
ESTIMATED PROJECT SCHEDULE
| Phase 1 | Phase 2 | Phase 3 | |
|---|---|---|---|
| Location | SR 417 to Narcoossee Rd | Narcoossee Rd to North of Cyrils Dr | Cyrils Dr to Nova Rd |
| Design Completion | Early 2027 | Early 2026 | Mid-2028 |
| Construction Start | 2027 | Late 2026 | 2029 |
| Construction Completion | 2032 | 2030 | 2032 |
*This schedule is subject to change.